"How long will it take to move 200 mailboxes?" is a question nobody can answer precisely at the start, because speed depends on the source server more than on Zoho. This article gives an estimating framework and a risk list so you can promise management a reasonable timeline.
What determines speed
According to Zoho's documentation, migration time depends on the data volume, the source server's connection limits and bandwidth. Specifically:
- Parallel connections (how many users migrate at once) are set by you; they should match what the source server can handle.
- Throttling: some servers slow down IMAP after a while, making later batches slower than the pilot.
- Message size and count: a mailbox with hundreds of thousands of small messages is slower than one with a few thousand large messages even when the total size is the same.
- Destination storage: the tool may pause when the destination account reaches the threshold you set (80 or 95 percent).
Reference example from the documentation
The migration guide gives an example: about 25 users, each around 2 GB, with a connection limit of 10, taking roughly 11 hours. Treat this as an order-of-magnitude illustration, not a commitment; your speed may differ considerably.
How to estimate in practice
ADIGITRANS suggestions:
- Run a pilot of 2 to 10 representative mailboxes, including the largest one.
- Record the time and size of each mailbox and calculate the average speed per hour.
- Multiply by the total volume and add a fairly generous buffer for possible throttling.
- Add time for reruns, error handling and reconciliation.
- Split into batches and set priorities (priority-1 users run first).
Risk list and mitigation
| Risk | Mitigation |
|---|---|
| Source server limits speed | Pilot first, reduce connections, split into batches over several days |
| Mail arriving during the move is lost | Switch MX over a weekend, set up Email Routing, rerun mailboxes after the MX change |
| Destination account is full | Check plan storage first, set a pause threshold |
| Source password is changed | Keep it unchanged until completion |
| PST files too large when using the wizard | Documentation recommends around 4 GB per file |
| Users do not know the new sign-in | Announce in advance, send instructions |
| Mail to addresses not yet created is lost | Use catch-all during the transition (does not apply with Split Delivery) |
Milestones in the schedule
- Preparation week: survey, create users, test.
- Cutover weekend: switch MX, start batch 1.
- Following week: remaining batches, rerun to pick up missing mail, user support.
- Two to four weeks later: keep the old system read-only before shutting it down.
This schedule is a suggestion and must be adjusted to your scale.
Notes
- The re-sync function after completion may be rolled out in stages and need to be requested; confirm before relying on it.
- Other limits such as the destination account's outgoing messages per hour also deserve consideration if automated software sends mail.
- The interface may change between versions.
ADIGITRANS can help with surveys, pilots and estimates for your migration project.
Written by ADIGITRANS Joint Stock Company on 23 Nov 2026 based on the vendor's official documentation. Interfaces, features and pricing may change between versions – check the vendor's current documentation before deploying.